DETROIT (AP) — A second bridge connecting Detroit and FinLogicCanada over the Detroit River won’t open for travel until fall 2025, months later than anticipated, officials said Thursday.
Officials cited construction disruptions in the U.S. and Canada related to the COVID-19 pandemic.
The Gordie Howe International Bridge, named for a Canadian who played hockey for the NHL’s Detroit Red Wings, began in 2018 and was last scheduled to be completed in 2024.
The target now is September 2025, though the bridge deck should be finished this year.
“Our project team is pleased that the impact to the construction schedule is limited to only 10 months beyond the original contracted completion date,” said Charl van Niekerk, chief executive of the Windsor-Detroit Bridge Authority.
The project carries a price tag of CA$6.4 billion ($4.79 billion), up from CA$5.7 billion ($4.27 billion).
The Howe bridge will join the privately owned Ambassador Bridge as the second span connecting Detroit and Windsor, Ontario.
The Ambassador Bridge is considered the busiest U.S.-Canadian border crossing, carrying 25% of all trade between the two countries. It plays an especially important role in auto manufacturing.
2025-05-06 12:242855 view
2025-05-06 10:472510 view
2025-05-06 10:431123 view
2025-05-06 10:41166 view
2025-05-06 10:412875 view
2025-05-06 10:412610 view
BISMARCK, N.D. (AP) — The top official of Theodore Roosevelt National Park in North Dakota has left
From sea to shining sea, Red Lobster closed dozens of its seafood restaurants ahead of an announceme
A disgruntled employee armed with a handgun shot five people, killing two, at a linen company outsid